{"id":8323,"date":"2021-03-23T08:40:46","date_gmt":"2021-03-23T13:40:46","guid":{"rendered":"https:\/\/cf.iisd.net\/itn\/?p=8323"},"modified":"2024-08-09T18:31:37","modified_gmt":"2024-08-09T16:31:37","slug":"kenya-prevails-in-a-geothermal-arbitration-brought-by-walam-energy-icsid-tribunal-reject-all-claimant-allegations","status":"publish","type":"post","link":"https:\/\/www.iisd.org\/itn\/2021\/03\/23\/kenya-prevails-in-a-geothermal-arbitration-brought-by-walam-energy-icsid-tribunal-reject-all-claimant-allegations\/","title":{"rendered":"Kenya prevails in a geothermal arbitration brought by WalAm Energy\u2014  ICSID tribunal rejects all claimant allegations"},"content":{"rendered":"<h2>WalAm Energy LLC v. The Republic of Kenya (<span class='tooltipsall tooltipsincontent classtoolTips18'>ICSID<\/span> Case No. ARB\/15\/7)<\/h2>\n<p>In an award dated July 10, 2020, an ICSID tribunal dismissed claims brought by WalAm Energy LCC (\u201cWalAm\u201d), a company incorporated in the United States and headquartered in Canada, over a geothermal project in the Republic of Kenya following Kenya\u2019s removal of WalAm\u2019s licence to explore and develop the Suswa geothermal concession. The tribunal found that Kenya validly removed WalAm\u2019s licence by declaring it forfeited due to its failure to perform any physical work during a continuous period of six months.<\/p>\n<h3>Background and claims<\/h3>\n<p>In a July 20, 2007 letter addressed to the Minister of Energy, WalAm submitted an application for an authority to explore. Later, on September 5, 2007, WalAm Energy obtained a licence from Kenya\u2019s Ministry of Energy, granting the entity exclusive rights to \u201center, explore, drill for and extract, produce, utilize and dispose of geothermal steam and associated geothermal resources.\u201d Separately, in a letter dated September 3, 2007, but signed by the minister on the same date as the licence, WalAm was given permission to explore for geothermal resources under Section 6(1) of the Geothermal Resources Act (the \u201cGRA\u201d).<\/p>\n<p>In February 2009, WalAm informed the minister by letter that it had completed the exploration of the Suswa geothermal concession, along with prospecting and pre-feasibility analyses, and proposed to proceed with the geothermal licence rights and initial drilling. At that time, WalAm also asked the government to discuss the possibility of entering into a power purchase agreement (PPA) due to WalAm\u2019s limited financial resources. Later in March, meetings between the government and WalAm representatives took place. Although Kenya engaged in preliminary discussions, a PPA was never concluded.<\/p>\n<p>In March 2009, GeothermEx issued a feasibility report. However, WalAm did not provide a work program to the government until February 2011. In March of that year, the work program was approved based on the understanding that the schedule would be strictly followed. By the end of the year, WalAm\u2019s project had failed to progress and adhere to the program\u2019s plan for that year.<\/p>\n<p>On March 18, 2012, the government wrote a show cause letter stressing that WalAm was in breach of the licence as it had not carried out sufficient work at Suswa over the previous five years. The government also stated that \u201cUnder normal practice, it takes five years from geothermal resource exploration to construction of such power plants\u201d (para. 284). On October 30, 2012, the Minister of Energy issued a forfeiture letter revoking WalAm\u2019s licence. In response, WalAm filed for arbitration against Kenya under the licence dispute resolution clause, claiming a breach of customary international law for unlawfully declaring the licence forfeited and seeking hundreds of millions of dollars in compensation and reinstatement of the licence.<\/p>\n<h3>Domestic law is the applicable law. Customary international law may apply through domestic law<\/h3>\n<p>As the licence had no applicable law provision, WalAm argued that by consenting to arbitrate disputes \u201cpursuant to\u201d the <span class='tooltipsall tooltipsincontent classtoolTips1'>ICSID Convention<\/span>, Kenya agreed to arbitrate claims arising under Kenyan law and rules of international law because the tribunal\u2019s jurisdiction is founded on the basis of Article 42(1) of the ICSID Convention and Kenyan law, which incorporates customary international law. This article provides that disputes in the absence of agreement between the parties on the applicable law should be decided \u201cunder the law of the Contracting State party to the dispute and such rules of international law as may be applicable\u201d (Article 42(1) of the ICSID Convention). The claimant further submitted that Kenyan law and customary international law were applicable because Kenya had expressly incorporated international law into its Constitution. Kenya, however, argued that only domestic law was applicable because that was the law under which the licence was issued.<\/p>\n<p>The tribunal upheld the respondent\u2019s argument and reasoned that under Article 42 (1) of the Convention, Kenyan law was the applicable law because that was the State party\u2019s law to the dispute and the law that applies to the legality of the licence. Also, the licence\u2019s existence and validity derive from domestic law, as the government issued it. The tribunal also added that customary international law could only be relevant when examining particular issues through local law because \u201ccustomary international law is incorporated into Kenyan law [&#8230;], but that would not change the applicable law\u201d for a particular issue. Customary international law would only apply to ancillary or general rules incorporated in Kenyan domestic law (para. 348).<\/p>\n<h3>Tribunal dismisses Kenya\u2019s allegations regarding the validity of the licence<\/h3>\n<p>Kenya argued that under its domestic law, WalAm never applied for a licence because its letter dated July 20, 2007, was an application for authority only to explore. Consequently, a valid licence was never issued because the Minister of Energy never received a licence application. Therefore, the licence was <em>void ab initio<\/em> because the GRA requirements were not only a \u201cmere formality\u201d as claimed by WalAm (para. 361). The tribunal rejected Kenya\u2019s arguments because the Ministry granted both despite WalAm\u2019s application only for authority. Certainly, Kenya intended to grant both the authority to explore and the licence. The tribunal further stressed that despite the lack of clarity about the circumstances in which the minister\u2019s licence came to be issued as the claimant only applied for an authority to explore, WalAm wished to obtain both authority to explore and a licence. Similarly, the minister intended to grant both and did so, considering that WalAm was compliant entirely with the GRA (para. 364).<\/p>\n<h3>Rightful declaration of forfeiture: Tribunal dismisses all grounds raised by the claimant<\/h3>\n<p>WalAm challenged the declaration\u2019s validity on different grounds (on <em>ultra vires<\/em>; unjust enrichment; good faith; unreasonableness; proportionality; improper purpose; relevant and irrelevant considerations; procedural fairness; consent; estoppel, and reliance on own wrong). The tribunal rejected all allegations.<\/p>\n<h3><em>The government acted within its legal power<\/em><\/h3>\n<p>WalAm first argued that the government acted beyond its legal power (i.e., <em>ultra vires<\/em>) when it declared the forfeiture of the licence on the basis that WalAm had failed to build the power plant in five years. The tribunal, however,\u00a0 reasoned that contrary to what WalAm argued, the notice of forfeiture should only be interpreted in light of the licence and the GRA. Therefore, it concluded that the Minister of Energy was entitled to rely on Section 11(1)(a) of the GRA and the licence if no exploration activities were carried out for a continuous period of six months and expressly did so on the notice of forfeiture (paras. 412\u2013428).<\/p>\n<h3>Failure to perform physical activity triggers the right to forfeit<\/h3>\n<p>WalAm also contended that the minister had no factual basis to rely on Section 11(1)(a) because the work WalAm had done before the forfeiture notice was served could be interpreted as work, considering work as any activity concerning the licence. To determine whether the claimant had carried out any work, the tribunal turned to the interpretation and meaning of the words \u201cin or under the land\u201d in the GRA, Section 11(1)(a), and \u201cin or under the licence area\u201d in the licence, clause 7(1)(a). The tribunal sided with the respondent\u2019s interpretation that both expressions required physical activity (paras. 438\u2013440). The tribunal further explained that this interpretation \u201creads the forfeiture provision in the context\u201d and was therefore not narrow and literal as argued by WalAm but \u201cconsistent with the object and purpose of the licence\u201d and the rights granted under it (para. 441).<\/p>\n<h3>Revocation of the licence was in good faith, reasonable and proportional<\/h3>\n<p>WalAm further argued that the licence\u2019s revocation was in bad faith because the government\u2019s ultimate goal was to transfer the licence rights to a public entity. The claimant further argued that the forfeiture was disproportionate and unreasonable under domestic law. The tribunal rejected these arguments on the basis that WalAm did not strictly adhere to the timetable. Moreover, given WalAm\u2019s long history of inability to deliver since the work program\u2019s approval on September 7, 2007, and to acquire sufficient financial resources to do so, the licence\u2019s revocation was lawful and therefore reasonable and proportional.<\/p>\n<h3>No failure to take into account relevant considerations or consider irrelevant ones<\/h3>\n<p>WalAm further argued that the government failed to take into account \u201crelevant considerations\u201d when it decided to declare the licence forfeited. It is well established under Kenyan law that the exercise of discretionary public power may be found to have failed if \u201cirrelevant considerations\u201d are taken into account or \u201crelevant considerations\u201d are disregarded. The tribunal rejected this argument, indicating that as previously determined in its analysis, the reason for the forfeiture to be issued was that \u201cno apparent efforts to explore and exploit the geothermal resources\u201d had been made, and this was not an irrelevant consideration (para. 471). Similarly, the tribunal further concluded that Kenya had not failed to take into account any \u201crelevant considerations.\u201d The claimant\u2019s belief that its obligations under the licence were suspended came from the expectations arising from its repeated statements that it needed a PPA to raise the funds that the infrastructure required to progress the project.<\/p>\n<p>For the tribunal, such an assertion was illegitimate because the Minister of Energy expressly rejected a PPA on several occasions. First, it explicitly removed WalAm\u2019s reference to a PPA in its application when issuing the exploration licence. Secondly, when the 2011 work program was approved, government representatives did not adopt WalAm\u2019s timetable for a PPA. Therefore, according to the tribunal, the claimant\u2019s inability to raise sufficient capital resulted from the WalAm\u2019s deficiencies and its inadequacy (para. 493).<\/p>\n<h3>Consent and estoppel: Kenya\u2019s conduct could not have formed the basis of an estoppel or waiver as alleged by the claimant<\/h3>\n<p>WalAm further argued that Kenya consented in writing to the claimant not performing work in or under the land until it had a PPA or while negotiations for a PPA were ongoing and that Kenya should be estopped from relying on them to perform to trigger rights to forfeiture. The tribunal dismissed this claim because WalAm failed to prove that the government had expressly stated in any of its communications or letters that it had consented to the investor not performing work \u201cin or under the land\u201d until the conclusion of a PPA. No statement of consent or express representation could find estoppel to that effect. Moreover, the government informed WalAm of the minister\u2019s dissatisfaction with the lack of progress and work on many occasions. It was made clear in communications that the licence was under threat of forfeiture.<\/p>\n<h3>No legitimate expectations, as claimant failed to establish any evidential basis and support for its claim<\/h3>\n<p>The tribunal considered that the claimant could not argue that it had a legitimate expectation that it would not be required to begin drilling before a PPA was in place based on the government\u2019s conduct. Accordingly, it concluded that WalAm did not \u201chave a legitimate expectation in the public law sense\u201d as it failed to show that \u201cstatements were made by or on behalf of the government inducing such reasonable expectation\u201d (para. 527)<\/p>\n<h3>Customary international law application: No breach of the minimum standard of treatment<\/h3>\n<p>WalAm invoked breaches of the customary international law minimum standard of treatment, arguing that Kenya had violated its duty to accord the claimant the minimum standard under Article 47 of the Kenyan Constitution and customary international law. According to the claimant, the government\u2019s obstructive conduct and refusal to act in good faith to negotiate a PPA prevented WalAm from moving forward and bringing the project into production.<\/p>\n<p>The tribunal noted that all elements put forward by WalAm capable of constituting unfair treatment in breach of the international law standard have been previously considered in the tribunal\u2019s analysis and rejected. The tribunal added that expropriation did not apply, and any claims on the merits would have failed. Also, the tribunal concluded that even if the absence of objections or silence from the government can in some instances generate legitimate expectations (see <em>Gold reserve v. Venezuela<\/em>),<a href=\"#_ftn1\" name=\"_ftnref1\"><sup>[1]<\/sup><\/a> it could not give rise, in this particular case, to any expectations in relation to the conclusion or failure to obtain a PPA in the investment treaty context (paras. 558\u2013561).<\/p>\n<h3>Costs<\/h3>\n<p>The respondent argued that all expenses should be borne by WalAm. Further, it added that even if the claimant were to prevail on liability, there should be an apportionment of costs to reflect the unnecessary costs caused by the claimant\u2019s conduct. In turn, the claimant argued that the respondent should bear the total arbitration costs incurred by the claimant.<\/p>\n<p>The tribunal stated that the ICSID Convention \u201cgives the widest discretion to allocate all costs of the arbitration\u201d and noted that the respondent\u2019s legal costs were significantly lower than the claimant\u2019s costs.<\/p>\n<p>Tribunal ordered WalAm to pay the respondent USD 648,857.75 for the respondent\u2019s portion of the arbitration costs and the sums of EUR 3,586,039.28 and USD 252,262.82 to cover 75% of the respondent\u2019s legal fees and expenses.<\/p>\n<p><em>Notes<\/em>: The tribunal was composed of Joe Smouha (president, nominated by the parties, British national), Swithin J. Munyantwali (claimant\u2019s appointee, British and Ugandan national) and James Spigelman (respondent\u2019s appointee, Australian national). The award of July 10, 2020, is available at<a href=\"https:\/\/www.iareporter.com\/articles\/revealed-award-in-dispute-over-kenyan-geothermal-energy-project-comes-to-light\/\"> https:\/\/www.iareporter.com\/articles\/revealed-award-in-dispute-over-kenyan-geothermal-energy-project-comes-to-light\/<\/a><\/p>\n<p><strong>Maria Bisila Torao<\/strong> is an international lawyer based in London. She holds an LL.M. in investment treaty arbitration from Uppsala University, an LL.M. in international commercial arbitration from Stockholm University, and a bachelor\u2019s degree in law from the University of Malaga.<\/p>\n<p><a href=\"#_ftnref1\" name=\"_ftn1\"><sup>[1]<\/sup><\/a><a href=\"https:\/\/www.italaw.com\/cases\/2727\"> Gold Reserve Inc. v. Bolivarian Republic of Venezuela, ICSID Case No. ARB(AF)\/09\/1<\/a><\/p>\n<p>&nbsp;<!--more--><\/p>\n<script type=\"text\/javascript\"> toolTips('.classtoolTips1','Convention on the Settlement of Investment Disputes between States and Nationals of Other States'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips18','International Centre for Settlement of Investment Disputes'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips63','Bilateral investment treaty'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips65','East African community'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips67','Energy Charter Treaty'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips72','Investment Court System'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips85','Organisation internationale du travail'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips86','Organizaci\u00f3n Mundial del Trabajo'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips100','investissement direct \u00e9tranger'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips104','responsabilit\u00e9 sociale des entreprises'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips106','asociaci\u00f3n p\u00fablica-privada'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips110','inversi\u00f3n extranjera directa'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips114','Sistema de Tribunales de Inversiones'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips116','European Commission'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips117','European Union'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips118','Union europ\u00e9enne'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips119','Uni\u00f3n Europea'); <\/script>","protected":false},"excerpt":{"rendered":"<p>WalAm Energy LLC v. The Republic of Kenya (<span class='tooltipsall tooltipsincontent classtoolTips18'>ICSID<\/span> Case No. ARB\/15\/7)<script type=\"text\/javascript\"> toolTips('.classtoolTips18','International Centre for Settlement of Investment Disputes'); <\/script><script type=\"text\/javascript\"> toolTips('.classtoolTips72','Investment Court System'); <\/script><\/p>\n","protected":false},"author":1,"featured_media":15869,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[15],"tags":[1950],"class_list":["post-8323","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-awards","tag-kenya"],"acf":[],"_links":{"self":[{"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/posts\/8323","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/comments?post=8323"}],"version-history":[{"count":0,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/posts\/8323\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/media\/15869"}],"wp:attachment":[{"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/media?parent=8323"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/categories?post=8323"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.iisd.org\/itn\/wp-json\/wp\/v2\/tags?post=8323"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}